Volume 14, Issue 37;   September 10, 2014: False Summits: I

False Summits: I

by

Mountaineers often experience "false summits," when just as they thought they were nearing the summit, it turns out that there is much more climbing to do. So it is in project work.
A view from the false summit of the Manitou incline in Colorado

A view looking down from the false summit of the Manitou Incline in Colorado. The incline follows the route of a funicular that is no longer in service. Note the gradual increase of steepness of the incline as it descends, followed by a section that is less steep. It is this configuration that creates false summits.

In project work, when we tackle the "easy parts" first, and then encounter a more difficult stretch, we expose ourselves to a risk of experiencing a false summit, because we cannot see past the more challenging section. Sending a team ahead to explore that part of the project can limit the risk of a false summit.

Photo (cc) AHodges7.

Projects are so notorious for overrunning their budgets and schedules that we all know what we mean by, "the second 90% of the work." Just as we feel like we're closing in on the goal, new tasks appear — things we overlooked, or things we were just clueless about. We can learn about how to deal with this by examining an experience from mountaineering — the false summit.

Some mountains are notorious for having false summits. One encounters a false summit when the contour of the terrain is such that what appears from below to be the summit is actually just a protruding ridge or shoulder that obstructs the view of the real summit — if you're lucky. If you're unlucky, the false summit merely obstructs your view of the next false summit. Either way, ascending further, it becomes clear what has happened, because there is more mountain above than first appeared.

Recognizing that the "summit" wasn't the summit can be discouraging. In physically trying situations, which are common in mountaineering, the added psychological stress and disappointment can actually threaten safety.

At work, the analog of encountering a false summit is the discovery that completing the project requires far more effort and time than we thought. After several such revelations, discouragement is common. The credibility of leaders becomes an issue, and that makes management more difficult. Failure looms.

Here are some tips for avoiding false summits in projects.

Have a good map
A map of the terrain is essential for planning your course up a mountain. The higher the peak, or the rougher the terrain, the more useful is a map. Still, things change. Maps aren't perfect.
In projects, In project work, we tend not to
employ advance reconnaissance
as often as we might
we must often make plans based on experience with other efforts, because we've never done what we're now attempting. That experience can be misleading, but it's the best we can do. Use plans with care.
Reconnaissance helps
In climbing, the more you know about the route, the more likely is success. At times, we send someone ahead to gather data that helps us determine the best course forward.
In project work, we tend not to employ advance reconnaissance as often as we might, because we tend to view as wasteful any activity that doesn't directly contribute to deliverables. Send someone ahead to reconnoiter. Focus groups, piloting, and prototypes are usually helpful.
Use locator technologies
Maps are helpful even if you know your location only approximately, but knowing exactly where you are makes maps even more useful. Locator technologies do help.
In project work, there is no equivalent of a GPS locator. But we can often benefit from periodically re-estimating the work remaining to be done, using the insight we've acquired from the work done so far.

We'll continue next time by exploring the psychology of the experience of false summits.  Next in this series Go to top Top  Next issue: False Summits: II  Next Issue

52 Tips for Leaders of Project-Oriented OrganizationsAre your projects always (or almost always) late and over budget? Are your project teams plagued by turnover, burnout, and high defect rates? Turn your culture around. Read 52 Tips for Leaders of Project-Oriented Organizations, filled with tips and techniques for organizational leaders. Order Now!

Your comments are welcome

Would you like to see your comments posted here? rbrendPtoGuFOkTSMQOzxner@ChacEgGqaylUnkmwIkkwoCanyon.comSend me your comments by email, or by Web form.

About Point Lookout

This article in its entirety was written by a 
          human being. No machine intelligence was involved in any way.Thank you for reading this article. I hope you enjoyed it and found it useful, and that you'll consider recommending it to a friend.

This article in its entirety was written by a human being. No machine intelligence was involved in any way.

Point Lookout is a free weekly email newsletter. Browse the archive of past issues. Subscribe for free.

Support Point Lookout by joining the Friends of Point Lookout, as an individual or as an organization.

Do you face a complex interpersonal situation? Send it in, anonymously if you like, and I'll give you my two cents.

Related articles

More articles on Project Management:

Stuffed bearsStart a Project Nursery
In a Project Nursery, professionals from across the entire organization collaborate to conceive of new projects. When all organizational elements help decide which projects to investigate, the menu they develop best suits organizational needs and capabilities.
Example of an unsecured driver-side floor mat trapping the accelerator pedal in a 2007 Toyota Lexus ES350Risk Management Risk: I
Risk Management Risk is the risk that a particular risk management plan is deficient. It's often overlooked, and therefore often unmitigated. We can reduce this risk by applying some simple procedures.
A piece of chocolate cakeEgo Depletion and Priority Setting
Setting priorities for tasks is tricky when we find the tasks unappealing, because we have limited energy for self-control. Here are some strategies for limiting these effects on priority setting.
Larix gmelinii forestSeven Planning Pitfalls: II
Plans are well known for working out differently from what we intended. Sometimes, the unintended outcome is due to external factors over which the planning team has little control. Two examples are priming effects and widely held but inapplicable beliefs.
Workers prepare the S-IC first stage in the transfer aisle of the Vehicle Assembly Building at NASA's Kennedy Space CenterLessons Not Learned: II
The planning fallacy is a cognitive bias that causes us to underestimate the cost and effort involved in projects large and small. Efforts to limit its effects are more effective when they're guided by interactions with other cognitive biases.

See also Project Management and Personal, Team, and Organizational Effectiveness for more related articles.

Forthcoming issues of Point Lookout

Typing a text message on a smartphoneComing May 15: Should I Write or Should I Call?
After we recognize the need to contact a colleague or colleagues to work out a way to move forward, we next must decide how to make contact. Phone? Videoconference? Text message? There are some simple criteria that can help with such decisions. Available here and by RSS on May 15.
Satrun during equinox — a composite of natural-color images from CassiniAnd on May 22: Rescheduling Collaborative Work
Rescheduling is what we do when the schedule we have now is so desperately unachievable that we must let go of it because when we look at it we can no longer decide whether to laugh or cry. The fear is that the new schedule might come to the same end. Available here and by RSS on May 22.

Coaching services

I offer email and telephone coaching at both corporate and individual rates. Contact Rick for details at rbrendPtoGuFOkTSMQOzxner@ChacEgGqaylUnkmwIkkwoCanyon.com or (650) 787-6475, or toll-free in the continental US at (866) 378-5470.

Get the ebook!

Past issues of Point Lookout are available in six ebooks:

Reprinting this article

Are you a writer, editor or publisher on deadline? Are you looking for an article that will get people talking and get compliments flying your way? You can have 500-1000 words in your inbox in one hour. License any article from this Web site. More info

Follow Rick

Send email or subscribe to one of my newsletters Follow me at LinkedIn Follow me at X, or share a post Subscribe to RSS feeds Subscribe to RSS feeds
The message of Point Lookout is unique. Help get the message out. Please donate to help keep Point Lookout available for free to everyone.
Technical Debt for Policymakers BlogMy blog, Technical Debt for Policymakers, offers resources, insights, and conversations of interest to policymakers who are concerned with managing technical debt within their organizations. Get the millstone of technical debt off the neck of your organization!
Go For It: Sometimes It's Easier If You RunBad boss, long commute, troubling ethical questions, hateful colleague? Learn what we can do when we love the work but not the job.
303 Tips for Virtual and Global TeamsLearn how to make your virtual global team sing.
101 Tips for Managing ChangeAre you managing a change effort that faces rampant cynicism, passive non-cooperation, or maybe even outright revolt?
101 Tips for Effective MeetingsLearn how to make meetings more productive — and more rare.
Exchange your "personal trade secrets" — the tips, tricks and techniques that make you an ace — with other aces, anonymously. Visit the Library of Personal Trade Secrets.
If your teams don't yet consistently achieve state-of-the-art teamwork, check out this catalog. Help is just a few clicks/taps away!
Ebooks, booklets and tip books on project management, conflict, writing email, effective meetings and more.