First things first: when referring to people in the abstract, I prefer words like "someone," "person," or "people." I dislike the word "resources," which, to me, evokes things like equipment, timber, and coalmines. OK. That's out of the way.
When team members have responsibilities to multiple teams, those teams all face risks. The unexpected happens. Priorities change. Schedules change. Time commitments cannot always be honored. We might try to schedule our efforts, but when team members belong to multiple teams, the plan and the reality are sometimes wildly different, even if the root cause of the trouble is elsewhere.
Here are four guidelines for sharing people more effectively than we often do.
- Front-load the activities of shared people
- Trouble sometimes arises in partner efforts. If resolving that trouble requires additional time from someone you share, you could lose access to that person. Moreover, even if the partner project goes smoothly, difficulties in other projects could result in schedule changes for the partner project, and the shared person might not be available at the time you scheduled.
- If possible, schedule your own efforts so that the work that shared people do happens early.
- Adjust effort estimates for interruption of flow
- During planning, when we estimate effort, we often assume that the person doing the work is doing nothing else. Since that assumption is invalid for people with divided responsibilities, and since juggling multiple assignments does have associated costs, our estimates tend to be lower than the actual time required.
- Make estimates that realistically account for the loss of time due to multiple assignments. When tracking actual effort data, track assignment multiplicity, too.
- Combine hours into the longest possible contiguous bursts
- To minimize Combine hours into the longest
possible contiguous burstslosses due to interruption of flow in the context of split assignments, combine hours of effort for each person into the largest possible contiguous chunks. Instead of one day per week for six weeks, schedule two days per week for three weeks, or four days in one week, and two days three weeks later. - You might have to negotiate with partner team leads, but when they understand the advantages of contiguous bursts, the negotiations are likely to be smooth.
- Avoid the "MS Project flat rate syndrome"
- Planners tend to use as weekly effort estimates for each person, the total estimated effort for each person divided by the task duration in weeks. Rarely does work actually proceed in this way. Even if it did, such a pattern maximizes the losses due to multiple assignments, because it maximally interrupts flow.
- Actual work is usually performed in bursts. Use your project planning software to schedule those bursts.
People with multiple assignments are usually less effective than they would be if they had only one assignment. And they might be called away at any time. Plan for it. Top Next Issue
Are your projects always (or almost always) late and over budget? Are your project teams plagued by turnover, burnout, and high defect rates? Turn your culture around. Read 52 Tips for Leaders of Project-Oriented Organizations, filled with tips and techniques for organizational leaders. Order Now!
Your comments are welcome
Would you like to see your comments posted here? rbrendPtoGuFOkTSMQOzxner@ChacEgGqaylUnkmwIkkwoCanyon.comSend me your comments by email, or by Web form.About Point Lookout
Thank you for reading this article. I hope you enjoyed it and found it useful, and that you'll consider recommending it to a friend.
This article in its entirety was written by a human being. No machine intelligence was involved in any way.
Point Lookout is a free weekly email newsletter. Browse the archive of past issues. Subscribe for free.
Support Point Lookout by joining the Friends of Point Lookout, as an individual or as an organization.
Do you face a complex interpersonal situation? Send it in, anonymously if you like, and I'll give you my two cents.
Related articles
More articles on Project Management:
- Flanking Maneuvers
- Historically, military logistics practice has provided a steady stream of innovations to many fields,
including project management. But project managers can learn even more if we investigate battlefield tactics.
- Beyond Our Control
- When bad things happen, despite our plans and our best efforts, we sometimes feel responsible. We failed.
We could have done more. But is that really true? Aren't some things beyond our control?
- Personnel-Sensitive Risks: I
- Some risks and the plans for managing them are personnel-sensitive in the sense that disclosure can
harm the enterprise or its people. Since most risk management plans are available to a broad internal
audience, personnel-sensitive risks cannot be managed in the customary way. Why not?
- Managing Non-Content Risks: II
- When we manage risk, we usually focus on those risks most closely associated with the tasks at hand
— content risks. But there are other risks, to which we pay less attention. Many of these are
outside our awareness. Here's Part II of an exploration of these non-content risks, emphasizing those
that relate to organizational politics.
- Seven Planning Pitfalls: III
- We usually attribute departures from plan to poor execution, or to "poor planning." But one
cause of plan ineffectiveness is the way we think when we set about devising plans. Three cognitive
biases that can play roles are the so-called Magical Number 7, the Ambiguity Effect, and the Planning Fallacy.
See also Project Management and Personal, Team, and Organizational Effectiveness for more related articles.
Forthcoming issues of Point Lookout
- Coming May 15: Should I Write or Should I Call?
- After we recognize the need to contact a colleague or colleagues to work out a way to move forward, we next must decide how to make contact. Phone? Videoconference? Text message? There are some simple criteria that can help with such decisions. Available here and by RSS on May 15.
- And on May 22: Rescheduling Collaborative Work
- Rescheduling is what we do when the schedule we have now is so desperately unachievable that we must let go of it because when we look at it we can no longer decide whether to laugh or cry. The fear is that the new schedule might come to the same end. Available here and by RSS on May 22.
Coaching services
I offer email and telephone coaching at both corporate and individual rates. Contact Rick for details at rbrendPtoGuFOkTSMQOzxner@ChacEgGqaylUnkmwIkkwoCanyon.com or (650) 787-6475, or toll-free in the continental US at (866) 378-5470.
Get the ebook!
Past issues of Point Lookout are available in six ebooks:
- Get 2001-2 in Geese Don't Land on Twigs (PDF, )
- Get 2003-4 in Why Dogs Wag (PDF, )
- Get 2005-6 in Loopy Things We Do (PDF, )
- Get 2007-8 in Things We Believe That Maybe Aren't So True (PDF, )
- Get 2009-10 in The Questions Not Asked (PDF, )
- Get all of the first twelve years (2001-2012) in The Collected Issues of Point Lookout (PDF, )
Are you a writer, editor or publisher on deadline? Are you looking for an article that will get people talking and get compliments flying your way? You can have 500-1000 words in your inbox in one hour. License any article from this Web site. More info
Follow Rick
Recommend this issue to a friend
Send an email message to a friend
rbrendPtoGuFOkTSMQOzxner@ChacEgGqaylUnkmwIkkwoCanyon.comSend a message to Rick
A Tip A Day feed
Point Lookout weekly feed